310 Permit Forms and Information
Online Platform for submitting 310 Permit applications
- Click ‘Apply for Permit’ and create an account before you begin.
Montana’s Natural Streambed and Land Preservation Act, also known as the 310 Law, is a state law that requires any person proposing a project that may physically alter or modify the beds or banks of a perennial stream, river, or spring on private or public land must first obtain a 310 Permit from their local conservation district. Permits are free of charge.
The purpose of the 310 Law is to ensure that projects on streams are carried out in ways that are not damaging to the stream or to adjoining landowners.
To learn more, please visit our Rules and Regulations page.
Conservation districts throughout Montana administer the 310 Law. Gallatin Conservation District administers the 310 Law within Gallatin County, outside of the 1949 Bozeman and Belgrade City limits. For projects within the 1949 city limits, contact Gallatin County.
To learn more, please visit our Rules and Regulations page.
The permitting process takes between 30 and 90 days. Once approved, a 310 permit is valid for one year. Permits decisions are made by the Gallatin Conservation District Board of Supervisors during the monthly meetings, which occur on the third Thursday of each month. Meetings are open to the public. Annual permits are also available for routine maintenance work, such as opening/clearing ditches, and valid for up to five to ten years.
1) Application Process
All information requested on the 310 application along with a plan and/or drawing of the proposed project and a site map must be provided. Incomplete applications may be rejected. Applications are reviewed and accepted at the monthly district meetings. After a 310 application is received, Montana Fish Wildlife and Parks is notified of the proposed project and may request an on-site inspection.
To ensure your application is submitted on time for review at the next district meeting, please see our Calendar.
2) Site Inspection Process
A team, consisting of the district resource conservationist, district supervisor, a Montana Fish, Wildlife, and Parks representative, and the applicant or applicant’s representative will meet to discuss the project on site. The applicant or their representative is entitled to be a team member for the purposes of making recommendations to the district. Team members may waive participation in the on-site inspection.
After an inspection is conducted, team members make recommendations to the district at a regular meeting. The applicant can waive participation, submit a team member report jointly with other team members (if in agreement with their recommendations), or submit a separate report.
If no inspection is required, the district may proceed with the application and the applicant will be notified of the supervisors’ decision.
3) Decision Process
The district will decide whether to approve, modify, or deny the project within 60 days of acceptance of the application. However, this time period can be extended if the district determines it necessary to collect further information. After receiving the supervisors’ decision, the applicant has 15 days to return the permit, signed to indicate agreement with the district’s decision. Unless otherwise stated on the supervisors’ decision form, the applicant must wait 15 days before proceeding with the project.
Considerations that must be addressed by the district in making their decision:
- The effects on soil erosion and sedimentation, considering the methods available to complete the project and the nature and economics of the various alternatives
- The effects of stream channel alteration
- The effects on streamflow, turbidity, and water quality caused by materials used or by removal of ground cover
- The effects on fish and aquatic habitat
- Whether there are modifications or alternative solutions that are reasonably practical that would reduce the disturbance to the stream and its environment and better accomplish the purpose of the project
- Whether the proposed project will create harmful flooding or erosion problems upstream or downstream
There is no fee for a 310 Permit. Applications can be picked up in the district office or downloaded on our website. Please check the calendar for application deadlines and note that an original signature from both the applicant and the landowner is required with each application. For questions, contact Gallatin Conservation District by calling 406-282-4350, emailing audra@gallatincd.org, or stopping in the office at 120 South 5th Street, Suite B104.
Additional permits are often required when performing a stream project. The 310 Joint Application form can be used to obtain permits from local, state, and federal agencies.
Please read the 310 Joint Applications Instructions linked above for a list of additional permits you may need to apply for using the 310 Joint Application Form.
There is an emergency provision in the 310 law to handle actions necessary to safeguard life or property, including growing crops, during periods of emergency. If a person takes an emergency action, the conservation district must be notified within 15 days in writing of the action taken and why. The emergency action will be reviewed and inspected by the conservation district. The district will decide whether the action was appropriate, must be modified, or must be removed and/or replaced.
It is a misdemeanor to initiate a project without a permit, to conduct activities outside the scope of the permit, to violate emergency procedures or to use prohibited materials in a project. Upon conviction of a misdemeanor, a person may be punished by a fine up to $500 or by a civil penalty not to exceed $500 per day for each day the person continues to alter the stream. In addition, the person may be required to restore the damaged stream to a condition as close to its prior condition as possible, as recommended by the District supervisors.
OTHER STREAM PERMITS ARE OFTEN NEEDED IN ADDITION TO THE 310 PERMIT. READ MORE ABOUT STREAM PERMITTING REQUIRED BY OTHER AGENCIES.
Examples of Projects Requiring a 310 Permit*:
- Channel Changes/Dredging
- New Irrigation Diversions
- Streambank Protection Projects
- Culvert Installation/Removal
- Bridge Installation/Removal
- Ford Crossings
*A permit may also be required if an existing project needs repair and/or alternations.
Examples of Prohibited Projects:
Unless specifically authorized by the board through a 310 permit, the following activities are prohibited.
- The placement of concrete in a stream as rock riprap
- The placement of road fill material in a stream
- The placement of debris or other material in a stream where it may erode or otherwise enter the stream
- Projects that permanently prevent fish migration
- Removal of streambank vegetation within the immediate banks of the stream, unless necessary for completion of the permitted project
- Excavation of streambed gravels
- Construction of an in-stream pond
If you see work being done and are unsure if the Conservation District is aware of it, first check out our Current Permits page to see a list of active 310 permits.
If the project in question does not show up on the Current Permits list, please check out our most recent board meeting agenda as they may include new projects or emergency applications that haven’t been updated to the current permits page yet.
If you don’t see the project in question on this list or in the recent meeting agenda, then any person may file a complaint form to notify the Gallatin CD of potentially unpermitted activity being performed outside the scope of work.
1. Is the stream NATURAL?
- Is there a natural source of water (e.g., springs, seeps, or runoff)? (Must answer YES)
- Is the water collecting in a channel that generally follows natural drainage patterns (i.e., flows in troughs that generally go perpendicular to the contour lines of a topographical map or survey)? (Likely characteristic, but not necessary)
- Does it show up as a “Natural Carrier” in the 1953 Water Resources Survey? (Supporting material)
- Do historical aerial photos indicate the presence of a channel or saturated soil? (Supporting material)
- Is the stream PERENNIAL?
- Does the stream flow continuously at all seasons of the year, except in the case of appropriation, impoundment, or extreme drought? (Must answer YES)
- If the stream carries diverted water, would it flow continuously without that diverted water (e.g., is there perennial flow above the diversion, or perennially flowing springs along the stream route)? (Must answer YES)
- Is it considered perennial on ancillary mapping sources (USGS topos, Forest Service maps, etc.)? (Supporting material)
- Does the stream have a defined CHANNEL (area from mean high water mark on one bank to mean high water mark on the opposite bank)?
- Has the flow of water caused physical characteristics that distinguish the channel from the area above it? (Must answer YES)
- Is the channel devoid of terrestrial (not hydrophilic) vegetation? (Must answer YES)
- Is the channel devoid of agricultural value? (Must answer YES)
Conservation Districts are the only entity in Montana that determines jurisdiction for 310 permitting.
The following manual is a very useful tool for anyone interested in performing a stream project or understanding stream function and management. This manual also includes sample engineering designs and templates.
Introduction & Table of Contents
Chapter 1 – Intro to Stream Permitting
Chapter 2 – Stream Form and Function
Chapter 3 – Addressing Streambank Erosion
Chapter 4 – Stream Crossings Introduction
Chapter 5 – Irrigation Diversion Structures
Appendix 1 – Rosgen Stream Types
Appendix 2 – River Restoration Analysis Tool and Design Criteria